Section 1: Purging Air from Secondary Divider Valve Lube-to-Lube Point Lines
Steps 1-6, refer to FIG. 6.
1. Install the line from the secondary divider valve to
the lube point, but do not completely tighten the
connection at the lube point.
2. Remove the performance indicator port plug or the
performance indicator from the working valve sec-
tion on the secondary divider valve assembly corre-
sponding to the outlet port and the line connected to
the lube point.
3. Attach a hand pump filled with clean, filtered lubri-
cant to the port on the secondary divider valve that
was opened in Step 2.
4. Operate the hand pump until air-free lubricant is
observed flowing from the line at the lubrication
point.
5. Tighten the fitting at the lubrication point while lubri-
cant is still flowing.
6. Remove the hand pump and reinstall the perfor-
mance indicator or indicator port plug removed in
Step 2.
NOTE: If check valves were not installed at the lubrica-
tion point, lubricant may continually drain out of the line
when the secondary port is open. Therefore, when
check valves are not used, the method for bleeding this
line is to tighten the line at both ends and repeatedly
cycle the secondary divider valve via hand pump opera-
tion until lubricant, free of air, flows from the lubrication
point