For a 480Y/277V three-phase wye panel with the 277V variant of the meter:
• Connect meter terminal A to the voltage disconnect phase A (red wire)
• Connect meter terminal B to the voltage disconnect phase B (black wire)
• Connect meter terminal C to the voltage disconnect phase C (blue wire)
• Connect meter neutral terminal to neutral bar in the voltage disconnect panel
(white wire)
• Connect earth wire to earth post using lug provided
• From the auxiliary power transformer, connect 120V auxiliary power to AUXA
and AUXN on the meter (see Figure 7)
Figure 7: PowerLogic EM4000 meter 480Y/277V three-phase wye service
connection
N
A
B
C
AUX_N
AUX_A
FROM PANEL
A
N