PowerLogic
TM
Series EM4000 930-134-01-A.00
Installation Guide 11/2013
16 ©2013 Schneider Electric All Rights Reserved
For a 600Y/347V or higher three-phase wye panel with potential transformers
with the 120V variant of the meter:
• Connect meter terminal A to the voltage disconnect phase A (red wire)
• Connect meter terminal B to the voltage disconnect phase B (black wire)
• Connect meter terminal C to the voltage disconnect phase C (blue wire)
• Connect meter neutral terminal to neutral bar in the voltage disconnect panel
(white wire)
• Connect earth wire to earth post using lug provided
• Install power supply shorting jumpers (see Figure 8)
NOTE: For the wiring of the potential transformers, see Figure 4.
Figure 8: PowerLogic EM4000 meter 600Y/347V or higher three-phase wye
service with potential transformers connection
Legend:
1 BX cable
2 Earth
3 Phase C (blue)
4 Phase B (black)
5 Shorting jumper
6 Sense voltage terminal block (J3)
7 Neutral (white)
8 Phase A (red)
9 0.75-inch (1.9-cm) strain relief
8
4
7
5
6
2
1
3
9