This section is intended to provide a high-level sequence for the installation
process and also a roadmap to the information in this book. It is also noted
where specific steps are covered in other books.
Plan and Prepare the Site
Complete this task by following the instructions provided in Chapter 2.
1. Determine what was ordered for the customer: DEFINITY System
Generic 3, number of cabinets and port networks, management
terminals, adjuncts, consoles, telephones, modems, external trunks, etc.
2. Locate DEFINITY System equipment room and lay out equipment room
floorplan for system cabinets, management terminal and desk, cross-
connect hardware and adjuncts, etc.
3. Lay out and ensure appropriate power for switch and management
terminal in equipment room and arrange for an electrician to install.
4. Lay out and ensure appropriate grounding in equipment room (refer to
Appendix A, "Approved Grounds").
5. Determine location of equipment closets where large cables can be
connected out into smaller ones.
6. Determine where external trunk lines come into the building and where
external trunk converters and adapters will be installed.
7. Determine an appropriate available port circuit on DEFINITY System for
each telephone, trunk, and peripheral connection needed and create a
provisioning plan.
Unpack the Cabinets
Complete this task by following the instructions provided in Chapter 3.
1. Unpack and inspect the cabinets.
2. Check circuit packs.
Install and Connect the Cabinets
Complete this task by following the instructions provided in Chapter 4.
1. Install earthquake floor mounting if needed (refer to Appendix A,
"Approved Grounds").
2. Position and stack cabinets.
3. Connect system cabinet grounds.