DEFINITY System Installation Roadmap
Issue 1 September 1995
1-5
Activate the System
Complete this task by following the instructions provided in Chapter 7.
1. Power up switch.
2. Log in to the system.
3. Set required country options.
4. Change craft password.
5. Set date and time.
6. Set system maintenance parameters, if Packet Controller (TN778 Circuit
Pack) is included.
7. Save and back up translations.
Test the System
Complete this task by following the instructions provided in Chapter 8.
1. Check the system status for each cabinet.
2. Check circuit pack configuration.
3. Test Time Division Multiplexer (TDM) bus in Processor Port Network
(PPN).
4. Test Tone-Clock boards.
5. Test Switch Processor Element (SPE) duplication memory shadowing link,
only for high and critical reliability systems.
6. Test duplicated Switch Processor Element (SPE) interchange, only for
high and critical reliability systems.
7. Test expansion interface boards, if present.
8. Test Time Division Multiplexer (TDM) for each Expansion Port Network
(EPN), if Expansion Port Networks (EPN) are present.
9. Test Tone-Clock for each Expansion Port Network (EPN), if Expansion
Port Networks (EPN) are present.
10. Test Tone-Clock interchange for each Expansion Port Network (EPN),
only for critical reliability systems with Expansion Port Networks (EPN)
present.
11. Test expansion interface exchange for each Expansion Port Network
(EPN), if Expansion Port Networks (EPNs) are present.
12. Check circuit pack configuration, again.
13. Save and back up translations again, if required.
14. Re-install front doors on switch cabinets.